Interconnection Queues / Tracker

Interconnection queue numbers

US interconnection queues held 2,061 GW of proposed generation and storage at year-end 2025. Completed projects took a median 60.8 months from request to operation in 2025. Berkeley Lab’s sample excludes large loads; the tracker reports those separately, alongside resource MW, historical outcomes and dated reform milestones.

242 readings · source access dates on every row · Readings CSV · Readings JSON

Generation and storage queues

Find the operator

Storage includes estimated hybrid MW in LBNL’s regional summaries. Nuclear uses reported project-level MW. Total includes other resources. Waits cover completed projects with measured dates, not today’s applicants. Inspect each reading and its calculation.

Active generation and storage

GW · 31 December 2025 ERCOT: 408 GW · 09. Active Cap. Region+Type: D271, D272, D273, D274, D275, D276, D277; GW × 1,000 ERCOT 408 MISO: 382.2 GW · 09. Active Cap. Region+Type: D439, D440, D441, D442, D443, D444, D445; GW × 1,000 MISO 382.2 CAISO: 191.3 GW · 09. Active Cap. Region+Type: D187, D188, D189, D190, D191, D192, D193; GW × 1,000 CAISO 191.3 SPP: 171.2 GW · 09. Active Cap. Region+Type: D775, D776, D777, D778, D779, D780, D781; GW × 1,000 SPP 171.2 PJM: 144.3 GW · 09. Active Cap. Region+Type: D607, D608, D609, D610, D611, D612, D613; GW × 1,000 PJM 144.3 NYISO: 29.2 GW · 09. Active Cap. Region+Type: D523, D524, D525, D526, D527, D528, D529; GW × 1,000 NYISO 29.2 ISO-NE: 14.8 GW · 09. Active Cap. Region+Type: D355, D356, D357, D358, D359, D360, D361; GW × 1,000 ISO-NE 14.8
One LBNL snapshot and population. Click a bar for its source and calculation. MW in requests are proposed capacity.

Request to commercial operation

median months · year reaching COD 020406080 2015: 37.8 months · n=164 2015 37.8 2016: 44 months · n=180 2017: 39.9 months · n=138 2017 2018: 41.9 months · n=152 2019: 46.5 months · n=153 2019 2020: 46.1 months · n=227 2021: 50 months · n=200 2021 2022: 55.2 months · n=176 2023: 55.7 months · n=265 2023 2024: 62.7 months · n=335 2025: 60.8 months · n=294 2025 60.8 LBNL sample · completed projects
These medians include development after study completion. They are historical elapsed times, not a promised wait for a new project.

Major utility queue samples

Scope and missing values

Utility figures exclude missing component MW; totals cover all reported resources. These are workbook entity groups, not every project in each company’s service area. Inspect each reading and its calculation.

Non-ISO utility samples complement the ISO/RTO totals. They do not provide service-territory totals for utilities inside an ISO. Load readings below can overlap these footprints and are kept separate.

Large-load and data center requests

Load services and operators

Each row retains its own stage and population. Conditional Batch Zero classifications, delivery-point requests and signed contracts measure different things; do not sum them.

Published requests and conditional or contracted load, by source date
Operator / observationMWRequests / sampleAs ofPopulation and qualifications
ERCOTConditional base load66,400 MW2042026-09-03Conditional Batch Zero classification; all qualifying large-load typesIncludes some energized loads. Conditional classification issued September 3; not an approval to energize.Report: ERCOT: September 2026 Batch Zero Update, PDF pages 1 and 6
ERCOTConditional studied load127,900 MW1582026-09-03Conditional Batch Zero classification; all qualifying large-load typesSource conflict: the chart on PDF page 6 says 125,400 MW instead of 127,900 MW. Summary value retained; do not add the two readings.Report: ERCOT: September 2026 Batch Zero Update, PDF page 1, summary
ERCOTConditional studied load (chart)125,400 MW1582026-09-03Conditional Batch Zero classification; all qualifying large-load typesSource conflict: summary on PDF page 1 says 127,900 MW. Chart value retained separately, not a second population.Report: ERCOT: September 2026 Batch Zero Update, PDF page 6, chart label
ERCOTExcluded from Batch Zero302,200 MW3732026-09-03Conditional Batch Zero classification; all qualifying large-load typesExcluded from this transitional study, not necessarily withdrawn from all future interconnection processes.Report: ERCOT: September 2026 Batch Zero Update, PDF page 6, excluded-load note
ERCOTLoad requests (preliminary)458,700 MW—2026-05-19Legacy LLIS study-status categories 1–6, not a forecast of realized demandPreliminary; ERCOT says site control and financial commitment are not established by these study categories. Separate RPG column is excluded because of possible overlap.Report: ERCOT: comments on NPRR1325 and PGRR145, PDF page 7: sum 23.9 + 16.8 + 9.6 + 36.1 + 39.6 + 332.7 GW; ×1,000
AEP OhioLoad requests (prior interest)30,000 MW—2026-02-12Pre-tariff expressions of interest, recalled in the February 2026 updateRetrospective stages and contracts have different populations. Contracted projects are scheduled progressively through 2035; MW are not energized demand.Report: AEP Ohio: February 13, 2026 tariff load update, Release paragraphs on contracts and tariff steps
AEP OhioPaid study requests13,022.7 MW—2026-02-12Requests that paid for a formal engineering study under the new tariffRetrospective stages and contracts have different populations. Contracted projects are scheduled progressively through 2035; MW are not energized demand.Report: AEP Ohio: February 13, 2026 tariff load update, Release paragraphs on contracts and tariff steps
AEP OhioNew-tariff contracted load5,642 MW—2026-02-12Binding contracts under the Data Center Tariff, as of February 12, 2026Retrospective stages and contracts have different populations. Contracted projects are scheduled progressively through 2035; MW are not energized demand.Report: AEP Ohio: February 13, 2026 tariff load update, Release paragraphs on contracts and tariff steps
AEP OhioPre-tariff contracted load12,219 MW—2026-02-12Contracts signed before the new tariffRetrospective stages and contracts have different populations. Contracted projects are scheduled progressively through 2035; MW are not energized demand.Report: AEP Ohio: February 13, 2026 tariff load update, Release paragraphs on contracts and tariff steps
AEP OhioTotal contracted load17,861 MW—2026-02-12New-tariff plus pre-tariff contracted data-center projectsRetrospective stages and contracts have different populations. Contracted projects are scheduled progressively through 2035; MW are not energized demand.Report: AEP Ohio: February 13, 2026 tariff load update, Release paragraphs on contracts and tariff steps
Dominion ZoneDelivery-point requests70,000 MW—2026-02-02Approximate load advancing through the Dominion Zone delivery-point queueCompany-reported requests summarized by the SCC on February 19. Separate from Dominion’s non-ISO generation sample and overlapping PJM’s footprint.Report: Virginia SCC: Dominion PUR-2026-00011 notice and hearing order, PDF page 2; SCC account of the February 2 application
Dominion ZoneRequests with assigned dates25,000 MW—2026-02-02Approximate load being processed with assigned connection dates through 2031Company-reported requests summarized by the SCC on February 19. Separate from Dominion’s non-ISO generation sample and overlapping PJM’s footprint.Report: Virginia SCC: Dominion PUR-2026-00011 notice and hearing order, PDF page 2; SCC account of the February 2 application
Salt River ProjectTransition cluster requests7,200 MW242025-10Inaugural transition cluster load impact study; results issued October 2025April 2026 presentation describes an earlier cluster. Sample is 24 customers; these are not necessarily 24 unique campuses.Report: SRP: Large Customer Integration Process presentation filed at Arizona Corporation Commission, PDF page 15: cluster results; total new load for 24 customers

Historical completion and withdrawal

Denominator

Capacity-weighted outcomes as of end-2025 for requests submitted in 2000–2020. Active and suspended capacity remain in the denominator. These rates describe an older cohort.

Historical outcomes by ISO/RTO · source: LBNL Queued Up 2026
OperatorOutcomeShare of requested MWCohort requests
CAISOCompletion rate8.2 %1,910
CAISOWithdrawal rate76.4 %1,910
ERCOTCompletion rate24.3 %1,553
ERCOTWithdrawal rate57.2 %1,553
ISO-NECompletion rate17.6 %827
ISO-NEWithdrawal rate76.5 %827
MISOCompletion rate14 %2,806
MISOWithdrawal rate75.1 %2,806
NYISOCompletion rate12 %1,035
NYISOWithdrawal rate81.3 %1,035
PJMCompletion rate13.3 %5,589
PJMWithdrawal rate77.8 %5,589
SPPCompletion rate13.8 %1,682
SPPWithdrawal rate75.5 %1,682

Queue reform milestones

How dates are read

A dated filing or decision is an event in the record. Scheduled dates are labelled; partial compliance and applications are not final approvals.

  1. PJM: Reliability Resource Initiative projects selected

    One-time expansion of Transition Cycle 2.

    Observation 2025-05-02 · Source accessed 2026-11-11
  2. SPP: Order 2023 first compliance filing accepted in part

    Historical stage; superseded by the second compliance acceptance.

    Observation 2025-06-26 · Source accessed 2026-11-11
  3. MISO: MISO announced FERC approval of ERAS

    Date is the announcement date, not an inferred order date.

    Observation 2025-07-22 · Source accessed 2026-11-11
  4. MISO: ERAS sunset announced

    Future sunset date as announced in 2025.

    Observation 2025-07-22 · Source accessed 2026-11-11
  5. PJM: Order 2023 compliance filing found partially compliant

    Dated order finding; not a statement of final compliance as of today.

    Observation 2025-07-24 · Source accessed 2026-11-11
  6. ERCOT: NPRR1267 status-report rule approved

    Approval date is distinct from implementation date.

    Observation 2025-07-31 · Source accessed 2026-11-11
  7. MISO: First ERAS study scheduled to begin

    Schedule as announced July 22; not a retrospective confirmation of completion.

    Observation 2025-09-02 · Source accessed 2026-11-11
  8. SPP: Order 2023 second compliance filing accepted

    Accepted effective June 26, 2025; docket ER24-2026-001/002.

    Observation 2026-01-22 · Source accessed 2026-11-11
  9. Dominion Zone: Large-load queue standards application filed

    Application proposes batch planning for delivery-point requests. Filing is not approval.

    Observation 2026-02-02 · Source accessed 2026-11-11
  10. PJM: Cycle 1 application window closed

    First-ready, first-served application intake; not completion of all interconnection studies.

    Observation 2026-04-27 · Source accessed 2026-11-11
  11. ERCOT: Legacy LLIS submission process ended

    Transition to the Batch Zero process.

    Observation 2026-07-10 · Source accessed 2026-11-11
  12. ERCOT: Batch Zero study and qualifying energization approvals paused

    Historical action covering new large-load data centers and crypto facilities; the report describes verification work still in progress.

    Observation 2026-08-03 · Source accessed 2026-11-11
  13. ERCOT: Conditional Batch Zero classifications issued

    Provisional; final inclusion/exclusion depends on verification.

    Observation 2026-09-03 · Source accessed 2026-11-11
  14. ERCOT: Verification and community-review report deadline stated

    Deadline as reported at the September board meeting; not a completed review.

    Observation 2026-09-14 · Source accessed 2026-11-11

Every sourced reading

Download CSV

242 sourced readings. Every numeric value opens its source; the record link explains its scope.

Readings, dates and source populations · accessed dates are separate from observation dates
PJM 2026-10-06Cycle 1 at-risk depositsAll resources 169,000 MW 617 Approximately 169 GW agreed to first at-risk depositsSource read
ERCOT 2026-09-14Reform milestoneProcess 2026-12-10 — Verification and community-review report deadline statedSource read
ERCOT 2026-09-03Conditional base loadLarge load 66,400 MW 204 Conditional Batch Zero classification; all qualifying large-load typesSource read
ERCOT 2026-09-03Conditional studied loadLarge load 127,900 MW 158 Conditional Batch Zero classification; all qualifying large-load typesSource read · SOURCE CONFLICT
ERCOT 2026-09-03Conditional studied load (chart)Large load 125,400 MW 158 Conditional Batch Zero classification; all qualifying large-load typesSource read · SOURCE CONFLICT
ERCOT 2026-09-03Excluded from Batch ZeroLarge load 302,200 MW 373 Conditional Batch Zero classification; all qualifying large-load typesSource read
ERCOT 2026-09-03Reform milestoneProcess 2026-09-03 — Conditional Batch Zero classifications issuedSource read
ERCOT 2026-08-03Reform milestoneProcess 2026-08-03 — Batch Zero study and qualifying energization approvals pausedSource read
ERCOT 2026-07-10Reform milestoneProcess 2026-07-10 — Legacy LLIS submission process endedSource read
ERCOT 2026-05-19Load requests (preliminary)Large load 458,700 MW — Legacy LLIS study-status categories 1–6, not a forecast of realized demandSource read
PJM 2026-04-27Cycle 1 initial applicationsAll resources 220,000 MW 811 Initial intake before technical screening and at-risk depositsSource read
PJM 2026-04-27Reform milestoneProcess 2026-04-27 — Cycle 1 application window closedSource read
AEP Ohio 2026-02-12Load requests (prior interest)Data centers 30,000 MW — Pre-tariff expressions of interest, recalled in the February 2026 updateSource read
AEP Ohio 2026-02-12New-tariff contracted loadData centers 5,642 MW — Binding contracts under the Data Center Tariff, as of February 12, 2026Source read
AEP Ohio 2026-02-12Paid study requestsData centers 13,022.7 MW — Requests that paid for a formal engineering study under the new tariffSource read
AEP Ohio 2026-02-12Pre-tariff contracted loadData centers 12,219 MW — Contracts signed before the new tariffSource read
AEP Ohio 2026-02-12Total contracted loadData centers 17,861 MW — New-tariff plus pre-tariff contracted data-center projectsSource read
Dominion Zone 2026-02-02Delivery-point requestsData centers 70,000 MW — Approximate load advancing through the Dominion Zone delivery-point queueSource read
Dominion Zone 2026-02-02Requests with assigned datesData centers 25,000 MW — Approximate load being processed with assigned connection dates through 2031Source read
Dominion Zone 2026-02-02Reform milestoneProcess 2026-02-02 — Large-load queue standards application filedSource read
SPP 2026-01-22Reform milestoneProcess 2026-01-22 — Order 2023 second compliance filing acceptedSource read
Arizona Public Service 2025-12-31Active requestsAll resources 149 projects — Active requests with entity=APS; each workbook row counted onceSource read
Arizona Public Service 2025-12-31Reported active capacityAll resources 48,371.6 MW 149 Active requests with entity=APS; reported component MW onlySource read
Arizona Public Service 2025-12-31Reported active capacityGas 350 MW 2 Active requests with entity=APS; reported component MW onlySource read
Arizona Public Service 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=APS; reported component MW onlySource read
Arizona Public Service 2025-12-31Reported active capacitySolar 23,555.5 MW 61 Active requests with entity=APS; reported component MW onlySource read
Arizona Public Service 2025-12-31Reported active capacityStorage 5,475.1 MW 83 Active requests with entity=APS; reported component MW onlySource read
Arizona Public Service 2025-12-31Reported active capacityWind 3,173 MW 9 Active requests with entity=APS; reported component MW onlySource read
Bonneville Power Administration 2025-12-31Active requestsAll resources 290 projects — Active requests with entity=BPA; each workbook row counted onceSource read
Bonneville Power Administration 2025-12-31Reported active capacityAll resources 129,877.5 MW 290 Active requests with entity=BPA; reported component MW onlySource read
Bonneville Power Administration 2025-12-31Reported active capacityGas 2,566 MW 7 Active requests with entity=BPA; reported component MW onlySource read
Bonneville Power Administration 2025-12-31Reported active capacityNuclear 1,390 MW 2 Active requests with entity=BPA; reported component MW onlySource read
Bonneville Power Administration 2025-12-31Reported active capacitySolar 43,645.4 MW 153 Active requests with entity=BPA; reported component MW onlySource read
Bonneville Power Administration 2025-12-31Reported active capacityStorage 60,413.9 MW 170 Active requests with entity=BPA; reported component MW onlySource read
Bonneville Power Administration 2025-12-31Reported active capacityWind 14,265.6 MW 55 Active requests with entity=BPA; reported component MW onlySource read
CAISO 2025-12-31Active capacityAll resources 191,330.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2025-12-31Completion rateAll resources 8.2 % 1,910 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
CAISO 2025-12-31Withdrawal rateAll resources 76.4 % 1,910 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
CAISO 2025-12-31Active capacityGas 2,212.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=CAISO; reported component MW onlySource read
CAISO 2025-12-31Active capacitySolar 69,288.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2025-12-31Active capacityStorage 111,563.1 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2025-12-31Active capacityWind 7,687.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
Dominion (non-ISO sample) 2025-12-31Active requestsAll resources 35 projects — Active requests with entity=Dominion; each workbook row counted onceSource read
Dominion (non-ISO sample) 2025-12-31Reported active capacityAll resources 4,086 MW 35 Active requests with entity=Dominion; reported component MW onlySource read
Dominion (non-ISO sample) 2025-12-31Reported active capacityGas 1,586.9 MW 12 Active requests with entity=Dominion; reported component MW onlySource read
Dominion (non-ISO sample) 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=Dominion; reported component MW onlySource read
Dominion (non-ISO sample) 2025-12-31Reported active capacitySolar 2,077.4 MW 19 Active requests with entity=Dominion; reported component MW onlySource read
Dominion (non-ISO sample) 2025-12-31Reported active capacityStorage 374 MW 12 Active requests with entity=Dominion; reported component MW onlySource read
Dominion (non-ISO sample) 2025-12-31Reported active capacityWind 0 MW 0 Active requests with entity=Dominion; reported component MW onlySource read
Duke Energy (non-ISO sample) 2025-12-31Active requestsAll resources 289 projects — Active requests with entity=Duke; each workbook row counted onceSource read
Duke Energy (non-ISO sample) 2025-12-31Reported active capacityAll resources 30,029.6 MW 289 Active requests with entity=Duke; reported component MW onlySource read
Duke Energy (non-ISO sample) 2025-12-31Reported active capacityGas 13,584.7 MW 66 Active requests with entity=Duke; reported component MW onlySource read
Duke Energy (non-ISO sample) 2025-12-31Reported active capacityNuclear 139 MW 5 Active requests with entity=Duke; reported component MW onlySource read
Duke Energy (non-ISO sample) 2025-12-31Reported active capacitySolar 7,588.8 MW 133 Active requests with entity=Duke; reported component MW onlySource read
Duke Energy (non-ISO sample) 2025-12-31Reported active capacityStorage 5,199.6 MW 41 Active requests with entity=Duke; reported component MW onlySource read
Duke Energy (non-ISO sample) 2025-12-31Reported active capacityWind 0 MW 0 Active requests with entity=Duke; reported component MW onlySource read
ERCOT 2025-12-31Active capacityAll resources 408,002.1 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2025-12-31Completion rateAll resources 24.3 % 1,553 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
ERCOT 2025-12-31Withdrawal rateAll resources 57.2 % 1,553 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
ERCOT 2025-12-31Active capacityGas 44,236 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=ERCOT; reported component MW onlySource read
ERCOT 2025-12-31Active capacitySolar 151,950.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2025-12-31Active capacityStorage 165,315.3 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2025-12-31Active capacityWind 44,676.4 MW — Active generation/storage at year end; LBNL published regional summarySource read
Idaho Power 2025-12-31Active requestsAll resources 47 projects — Active requests with entity=IP; each workbook row counted onceSource read
Idaho Power 2025-12-31Reported active capacityAll resources 9,002.6 MW 47 Active requests with entity=IP; reported component MW onlySource read
Idaho Power 2025-12-31Reported active capacityGas 1,257.5 MW 5 Active requests with entity=IP; reported component MW onlySource read
Idaho Power 2025-12-31Reported active capacityNuclear 45 MW 1 Active requests with entity=IP; reported component MW onlySource read
Idaho Power 2025-12-31Reported active capacitySolar 4,634.2 MW 26 Active requests with entity=IP; reported component MW onlySource read
Idaho Power 2025-12-31Reported active capacityStorage 2,566.8 MW 31 Active requests with entity=IP; reported component MW onlySource read
Idaho Power 2025-12-31Reported active capacityWind 499 MW 4 Active requests with entity=IP; reported component MW onlySource read
ISO-NE 2025-12-31Active capacityAll resources 14,783.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2025-12-31Completion rateAll resources 17.6 % 827 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
ISO-NE 2025-12-31Withdrawal rateAll resources 76.5 % 827 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
ISO-NE 2025-12-31Active capacityGas 74.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=ISO-NE; reported component MW onlySource read
ISO-NE 2025-12-31Active capacitySolar 1,584.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2025-12-31Active capacityStorage 7,067.3 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2025-12-31Active capacityWind 6,049.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2025-12-31Active capacityAll resources 382,181.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2025-12-31Completion rateAll resources 14 % 2,806 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
MISO 2025-12-31Withdrawal rateAll resources 75.1 % 2,806 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
MISO 2025-12-31Active capacityGas 70,867.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2025-12-31Reported active capacityNuclear 2,170.1 MW 8 Active requests with entity=MISO; reported component MW onlySource read
MISO 2025-12-31Active capacitySolar 165,706.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2025-12-31Active capacityStorage 87,063.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2025-12-31Active capacityWind 46,728 MW — Active generation/storage at year end; LBNL published regional summarySource read
NV Energy 2025-12-31Active requestsAll resources 134 projects — Active requests with entity=NVE; each workbook row counted onceSource read
NV Energy 2025-12-31Reported active capacityAll resources 34,714.8 MW 134 Active requests with entity=NVE; reported component MW onlySource read
NV Energy 2025-12-31Reported active capacityGas 5,000.6 MW 13 Active requests with entity=NVE; reported component MW onlySource read
NV Energy 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=NVE; reported component MW onlySource read
NV Energy 2025-12-31Reported active capacitySolar 19,557.6 MW 60 Active requests with entity=NVE; reported component MW onlySource read
NV Energy 2025-12-31Reported active capacityStorage 5,992.9 MW 75 Active requests with entity=NVE; reported component MW onlySource read
NV Energy 2025-12-31Reported active capacityWind 0 MW 1 Active requests with entity=NVE; reported component MW onlySource read
NYISO 2025-12-31Active capacityAll resources 29,249.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2025-12-31Completion rateAll resources 12 % 1,035 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
NYISO 2025-12-31Withdrawal rateAll resources 81.3 % 1,035 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
NYISO 2025-12-31Active capacityGas 0 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=NYISO; reported component MW onlySource read
NYISO 2025-12-31Active capacitySolar 8,757.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2025-12-31Active capacityStorage 13,201 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2025-12-31Active capacityWind 7,290.3 MW — Active generation/storage at year end; LBNL published regional summarySource read
PacifiCorp 2025-12-31Active requestsAll resources 275 projects — Active requests with entity=PacifiCorp; each workbook row counted onceSource read
PacifiCorp 2025-12-31Reported active capacityAll resources 49,018.6 MW 275 Active requests with entity=PacifiCorp; reported component MW onlySource read
PacifiCorp 2025-12-31Reported active capacityGas 5,081.6 MW 24 Active requests with entity=PacifiCorp; reported component MW onlySource read
PacifiCorp 2025-12-31Reported active capacityNuclear 1,500 MW 3 Active requests with entity=PacifiCorp; reported component MW onlySource read
PacifiCorp 2025-12-31Reported active capacitySolar 26,186.2 MW 153 Active requests with entity=PacifiCorp; reported component MW onlySource read
PacifiCorp 2025-12-31Reported active capacityStorage 10,209.1 MW 170 Active requests with entity=PacifiCorp; reported component MW onlySource read
PacifiCorp 2025-12-31Reported active capacityWind 5,968.9 MW 32 Active requests with entity=PacifiCorp; reported component MW onlySource read
PJM 2025-12-31Active capacityAll resources 144,277.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2025-12-31Completion rateAll resources 13.3 % 5,589 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
PJM 2025-12-31Withdrawal rateAll resources 77.8 % 5,589 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
PJM 2025-12-31Active capacityGas 12,723.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2025-12-31Reported active capacityNuclear 1,551.9 MW 6 Active requests with entity=PJM; reported component MW onlySource read
PJM 2025-12-31Active capacitySolar 67,795.4 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2025-12-31Active capacityStorage 42,676.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2025-12-31Active capacityWind 19,325.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
Portland General Electric 2025-12-31Active requestsAll resources 23 projects — Active requests with entity=PGE; each workbook row counted onceSource read
Portland General Electric 2025-12-31Reported active capacityAll resources 6,418 MW 23 Active requests with entity=PGE; reported component MW onlySource read
Portland General Electric 2025-12-31Reported active capacityGas 0 MW 0 Active requests with entity=PGE; reported component MW onlySource read
Portland General Electric 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=PGE; reported component MW onlySource read
Portland General Electric 2025-12-31Reported active capacitySolar 2,783 MW 6 Active requests with entity=PGE; reported component MW onlySource read
Portland General Electric 2025-12-31Reported active capacityStorage 2,635 MW 18 Active requests with entity=PGE; reported component MW onlySource read
Portland General Electric 2025-12-31Reported active capacityWind 1,000 MW 5 Active requests with entity=PGE; reported component MW onlySource read
Public Service Company of New Mexico 2025-12-31Active requestsAll resources 75 projects — Active requests with entity=PNM; each workbook row counted onceSource read
Public Service Company of New Mexico 2025-12-31Reported active capacityAll resources 13,402.2 MW 75 Active requests with entity=PNM; reported component MW onlySource read
Public Service Company of New Mexico 2025-12-31Reported active capacityGas 438.6 MW 4 Active requests with entity=PNM; reported component MW onlySource read
Public Service Company of New Mexico 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=PNM; reported component MW onlySource read
Public Service Company of New Mexico 2025-12-31Reported active capacitySolar 7,113.8 MW 41 Active requests with entity=PNM; reported component MW onlySource read
Public Service Company of New Mexico 2025-12-31Reported active capacityStorage 4,017 MW 48 Active requests with entity=PNM; reported component MW onlySource read
Public Service Company of New Mexico 2025-12-31Reported active capacityWind 1,564.8 MW 7 Active requests with entity=PNM; reported component MW onlySource read
Southern Company 2025-12-31Active requestsAll resources 145 projects — Active requests with entity=SOCO; each workbook row counted onceSource read
Southern Company 2025-12-31Reported active capacityAll resources 31,407.7 MW 145 Active requests with entity=SOCO; reported component MW onlySource read
Southern Company 2025-12-31Reported active capacityGas 13,413.3 MW 38 Active requests with entity=SOCO; reported component MW onlySource read
Southern Company 2025-12-31Reported active capacityNuclear 421 MW 12 Active requests with entity=SOCO; reported component MW onlySource read
Southern Company 2025-12-31Reported active capacitySolar 11,714.4 MW 72 Active requests with entity=SOCO; reported component MW onlySource read
Southern Company 2025-12-31Reported active capacityStorage 5,859 MW 41 Active requests with entity=SOCO; reported component MW onlySource read
Southern Company 2025-12-31Reported active capacityWind 0 MW 0 Active requests with entity=SOCO; reported component MW onlySource read
SPP 2025-12-31Active capacityAll resources 171,159.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2025-12-31Completion rateAll resources 13.8 % 1,682 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
SPP 2025-12-31Withdrawal rateAll resources 75.5 % 1,682 Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020Source read
SPP 2025-12-31Active capacityGas 34,995.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=SPP; reported component MW onlySource read
SPP 2025-12-31Active capacitySolar 54,945.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2025-12-31Active capacityStorage 50,849.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2025-12-31Active capacityWind 27,291.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
Tennessee Valley Authority 2025-12-31Active requestsAll resources 97 projects — Active requests with entity=TVA; each workbook row counted onceSource read
Tennessee Valley Authority 2025-12-31Reported active capacityAll resources 23,484.6 MW 97 Active requests with entity=TVA; reported component MW onlySource read
Tennessee Valley Authority 2025-12-31Reported active capacityGas 15,086.6 MW 22 Active requests with entity=TVA; reported component MW onlySource read
Tennessee Valley Authority 2025-12-31Reported active capacityNuclear 576 MW 8 Active requests with entity=TVA; reported component MW onlySource read
Tennessee Valley Authority 2025-12-31Reported active capacitySolar 5,287 MW 42 Active requests with entity=TVA; reported component MW onlySource read
Tennessee Valley Authority 2025-12-31Reported active capacityStorage 2,347 MW 21 Active requests with entity=TVA; reported component MW onlySource read
Tennessee Valley Authority 2025-12-31Reported active capacityWind 0 MW 0 Active requests with entity=TVA; reported component MW onlySource read
US (LBNL sample) 2025-12-31Active capacityAll resources 2,061,327.5 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2025-12-31Active capacityGas 252,834.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2025-12-31Active capacitySolar 772,574.1 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2025-12-31Active capacityStorage 749,307.4 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2025-12-31Active capacityWind 219,745.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
Xcel Public Service Colorado 2025-12-31Active requestsAll resources 102 projects — Active requests with entity=PSCo; each workbook row counted onceSource read
Xcel Public Service Colorado 2025-12-31Reported active capacityAll resources 24,132.3 MW 102 Active requests with entity=PSCo; reported component MW onlySource read
Xcel Public Service Colorado 2025-12-31Reported active capacityGas 2,694 MW 11 Active requests with entity=PSCo; reported component MW onlySource read
Xcel Public Service Colorado 2025-12-31Reported active capacityNuclear 0 MW 0 Active requests with entity=PSCo; reported component MW onlySource read
Xcel Public Service Colorado 2025-12-31Reported active capacitySolar 10,590.3 MW 48 Active requests with entity=PSCo; reported component MW onlySource read
Xcel Public Service Colorado 2025-12-31Reported active capacityStorage 1,483 MW 33 Active requests with entity=PSCo; reported component MW onlySource read
Xcel Public Service Colorado 2025-12-31Reported active capacityWind 8,468.5 MW 30 Active requests with entity=PSCo; reported component MW onlySource read
Salt River Project 2025-10Transition cluster requestsLarge load 7,200 MW 24 Inaugural transition cluster load impact study; results issued October 2025Source read
MISO 2025-09-02Reform milestoneProcess 2025-09-02 — First ERAS study scheduled to beginSource read
ERCOT 2025-07-31Reform milestoneProcess 2025-07-31 — NPRR1267 status-report rule approvedSource read
PJM 2025-07-24Reform milestoneProcess 2025-07-24 — Order 2023 compliance filing found partially compliantSource read
MISO 2025-07-22Reform milestoneProcess 2025-07-22 — MISO announced FERC approval of ERASSource read
MISO 2025-07-22Reform milestoneProcess 2027-08-31 — ERAS sunset announcedSource read
SPP 2025-06-26Reform milestoneProcess 2025-06-26 — Order 2023 first compliance filing accepted in partSource read
PJM 2025-05-02RRI selected energy capacityAll resources 11,793 MW 51 Summer submitted energy MW, not UCAPSource read
PJM 2025-05-02RRI selected UCAPAll resources 9,361 MW 51 Unforced capacity contribution of selected projectsSource read
PJM 2025-05-02Reform milestoneProcess 2025-05-02 — Reliability Resource Initiative projects selectedSource read
CAISO 2025Median request to CODAll resources 109.6 months 14 Projects reaching commercial operation in 2025, with measured datesSource read
ERCOT 2025Median request to CODAll resources 48 months 74 Projects reaching commercial operation in 2025, with measured datesSource read
PJM 2025Median request to CODAll resources 82.6 months 46 Projects reaching commercial operation in 2025, with measured datesSource read
SPP 2025Median request to CODAll resources 56.1 months 138 Projects reaching commercial operation in 2025, with measured datesSource read
US (LBNL sample) 2025Median request to CODAll resources 60.8 months 294 Projects reaching commercial operation in 2025, with measured datesSource read
CAISO 2024-12-31Active capacityAll resources 272,763 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2024-12-31Active capacityGas 3,464.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2024-12-31Active capacitySolar 90,856.1 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2024-12-31Active capacityStorage 167,109.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2024-12-31Active capacityWind 10,742 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2024-12-31Active capacityAll resources 346,060.1 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2024-12-31Active capacityGas 22,783.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2024-12-31Active capacitySolar 139,424.3 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2024-12-31Active capacityStorage 151,633.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
ERCOT 2024-12-31Active capacityWind 31,988.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2024-12-31Active capacityAll resources 45,589.4 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2024-12-31Active capacityGas 129.1 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2024-12-31Active capacitySolar 5,310 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2024-12-31Active capacityStorage 21,575.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
ISO-NE 2024-12-31Active capacityWind 18,532.1 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2024-12-31Active capacityAll resources 447,512.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2024-12-31Active capacityGas 26,425.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2024-12-31Active capacitySolar 242,188 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2024-12-31Active capacityStorage 113,166.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
MISO 2024-12-31Active capacityWind 54,111.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2024-12-31Active capacityAll resources 78,485.4 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2024-12-31Active capacityGas 1,244.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2024-12-31Active capacitySolar 16,882.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2024-12-31Active capacityStorage 37,050.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
NYISO 2024-12-31Active capacityWind 23,258.4 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2024-12-31Active capacityAll resources 211,458.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2024-12-31Active capacityGas 7,893.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2024-12-31Active capacitySolar 103,409.2 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2024-12-31Active capacityStorage 64,317.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
PJM 2024-12-31Active capacityWind 35,641 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2024-12-31Active capacityAll resources 142,427.7 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2024-12-31Active capacityGas 15,104.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2024-12-31Active capacitySolar 57,937.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2024-12-31Active capacityStorage 38,532.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
SPP 2024-12-31Active capacityWind 30,424.4 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2024-12-31Active capacityAll resources 2,290,386.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2024-12-31Active capacityGas 136,224.6 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2024-12-31Active capacitySolar 956,482.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2024-12-31Active capacityStorage 890,733.9 MW — Active generation/storage at year end; LBNL published regional summarySource read
US (LBNL sample) 2024-12-31Active capacityWind 270,966.8 MW — Active generation/storage at year end; LBNL published regional summarySource read
CAISO 2024Median request to CODAll resources 93.9 months 14 Projects reaching commercial operation in 2024, with measured datesSource read
ERCOT 2024Median request to CODAll resources 43.5 months 95 Projects reaching commercial operation in 2024, with measured datesSource read
MISO 2024Median request to CODAll resources 73.2 months 45 Projects reaching commercial operation in 2024, with measured datesSource read
PJM 2024Median request to CODAll resources 70.3 months 60 Projects reaching commercial operation in 2024, with measured datesSource read
SPP 2024Median request to CODAll resources 67.7 months 56 Projects reaching commercial operation in 2024, with measured datesSource read
US (LBNL sample) 2024Median request to CODAll resources 62.7 months 335 Projects reaching commercial operation in 2024, with measured datesSource read
CAISO 2023Median request to CODAll resources 100.4 months 12 Projects reaching commercial operation in 2023, with measured datesSource read
ERCOT 2023Median request to CODAll resources 45.5 months 63 Projects reaching commercial operation in 2023, with measured datesSource read
MISO 2023Median request to CODAll resources 58.3 months 27 Projects reaching commercial operation in 2023, with measured datesSource read
NYISO 2023Median request to CODAll resources 87.3 months 5 Projects reaching commercial operation in 2023, with measured datesSource read
PJM 2023Median request to CODAll resources 66.9 months 64 Projects reaching commercial operation in 2023, with measured datesSource read
SPP 2023Median request to CODAll resources 40.3 months 44 Projects reaching commercial operation in 2023, with measured datesSource read
US (LBNL sample) 2023Median request to CODAll resources 55.7 months 265 Projects reaching commercial operation in 2023, with measured datesSource read
US (LBNL sample) 2022Median request to CODAll resources 55.2 months 176 Projects reaching commercial operation in 2022, with measured datesSource read
US (LBNL sample) 2021Median request to CODAll resources 50 months 200 Projects reaching commercial operation in 2021, with measured datesSource read
US (LBNL sample) 2020Median request to CODAll resources 46.1 months 227 Projects reaching commercial operation in 2020, with measured datesSource read
US (LBNL sample) 2019Median request to CODAll resources 46.5 months 153 Projects reaching commercial operation in 2019, with measured datesSource read
US (LBNL sample) 2018Median request to CODAll resources 41.9 months 152 Projects reaching commercial operation in 2018, with measured datesSource read
US (LBNL sample) 2017Median request to CODAll resources 39.9 months 138 Projects reaching commercial operation in 2017, with measured datesSource read
US (LBNL sample) 2016Median request to CODAll resources 44 months 180 Projects reaching commercial operation in 2016, with measured datesSource read
US (LBNL sample) 2015Median request to CODAll resources 37.8 months 164 Projects reaching commercial operation in 2015, with measured datesSource read

LBNL readings adapted from Lawrence Berkeley National Laboratory and GridTracker, Queued Up 2026, CC BY 4.0. Workbook retrieval and calculation notes. Operator reports retain their cited authorship.