PJM: Cycle 1 at-risk deposits

169,000 MW

From PJM: October 6, 2026 Pennsylvania House testimony · PDF page 7 (printed page 6), Further Generation Interconnection Queue Acceleration section

All resources · observation 2026-10-06. Approximately 169 GW agreed to first at-risk deposits. A later stage of the initial Cycle 1 population; 98 projects withdrew at this step.

Source accessed . Queue readings hub · PJM Interconnection listing

Measurement and population

Definitions and derivation
Operator / scope The operator or geographic population named by the source.
PJM 1
Measurement The measured stage, capacity, outcome, duration or dated reform event.
Cycle 1 at-risk deposits 1
Resource / load type Resource component or load population. Wind includes onshore and offshore; storage includes batteries and other storage.
All resources 1
Observation date Snapshot, cohort year or reported event date, retaining source precision. Separate from the source access date.
2026-10-06 1
Value Numeric measurement; interpret with unit, basis and note. Null for a dated milestone.
169,000 1
Unit MW, projects, percent, months or date. Capacity is not energy or dependable capacity unless explicitly stated.
MW 1
Population and denominator Population, study stage, status filter or outcome denominator for this reading.
Approximately 169 GW agreed to first at-risk deposits 1
Source locator / calculation Workbook sheet and cells or report section, including explicit conversions and derivations.
PDF page 7 (printed page 6), Further Generation Interconnection Queue Acceleration section 1
Requests / sample Number of projects or requests supporting the measurement where available; resource counts may overlap for hybrids.
617 1
Coverage and qualifications Source limitations, conflicts, missing component MW and distinctions needed to interpret this reading.
A later stage of the initial Cycle 1 population; 98 projects withdrew at this step. 1

Dated sources

  1. PJM: October 6, 2026 Pennsylvania House testimony accessed 2026-11-11