PJM: Completion rate

13.3 %

From LBNL and GridTracker: Queued Up 2026 workbook · 25. Comp. Rate Region: C31 / SUM(B31:E31) × 100

All resources · observation 2025-12-31. Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020. Denominator includes active, operational, withdrawn and suspended capacity. Not a probability estimate for a new request.

Source accessed . Queue readings hub · PJM Interconnection listing

Measurement and population

Definitions and derivation
Operator / scope The operator or geographic population named by the source.
PJM 1
Measurement The measured stage, capacity, outcome, duration or dated reform event.
Completion rate 1
Resource / load type Resource component or load population. Wind includes onshore and offshore; storage includes batteries and other storage.
All resources 1
Observation date Snapshot, cohort year or reported event date, retaining source precision. Separate from the source access date.
2025-12-31 1
Value Numeric measurement; interpret with unit, basis and note. Null for a dated milestone.
13.294 1
Unit MW, projects, percent, months or date. Capacity is not energy or dependable capacity unless explicitly stated.
% 1
Population and denominator Population, study stage, status filter or outcome denominator for this reading.
Capacity-weighted outcomes at end-2025 for requests submitted 2000–2020 1
Source locator / calculation Workbook sheet and cells or report section, including explicit conversions and derivations.
25. Comp. Rate Region: C31 / SUM(B31:E31) × 100 1
Requests / sample Number of projects or requests supporting the measurement where available; resource counts may overlap for hybrids.
5,589 1
Coverage and qualifications Source limitations, conflicts, missing component MW and distinctions needed to interpret this reading.
Denominator includes active, operational, withdrawn and suspended capacity. Not a probability estimate for a new request. 1

Dated sources

  1. LBNL and GridTracker: Queued Up 2026 workbook accessed 2026-11-11
  2. Pinned public workbook mirror used for extraction; see methodology accessed 2026-11-11

Workbook readings are adapted from Lawrence Berkeley National Laboratory and GridTracker, Queued Up 2026, CC BY 4.0. The pinned mirror was used for extraction; see retrieval provenance.