Public interconnection queues: ISOs, RTOs and utilities

Every operator in this table publishes its own queue, and no two publish it the same way. SPP gives a public listing with CSV download, PJM exports full or filtered lists in XLS and XML, ISO-NE publishes expected operation and synchronization dates, ERCOT issues a monthly status report and NESO refreshes its register every Tuesday and Friday. MISO sets the application fee at $7,600 and security at $8,000 per MW studied.

18 listingsChecked

Alberta Electric System Operator (AESO)Project list, interactive map and Power BI dashboardsGeneration, energy storage and load facilities——In-progress with accepted SASR; recently energized and cancelled projectsMonthly project reporting2026-11-11
Bonneville Power Administration (BPA)Request queue and queue mapLarge and small generation; line and load connections—FERC Order 845 study-completed/delayed report——2026-11-11
California ISO (CAISO)————Active, complete and withdrawn facilities—2026-11-11
Dominion Energy—————Queue status quarterly; queue performance semi-annually2026-11-11
Duke EnergyDuke Energy Progress generation study results downloadable from OASIS Generator Interconnection Information folderDistributed renewable generation and storage————2026-11-11
ERCOT—Planned generation in ERCOT region———Monthly GIS reports2026-11-11
Independent Electricity System Operator (IESO)—Transmission, load, generation and ancillary servicesQueue, applicant, transmission zone, type and sizeApplication date and proposed in-service dateActive means assessment/addendum work remains in progress—2026-11-11
ISO New EnglandPublic queue with PDF and XLSX export guidanceNew/uprated generation, elective transmission upgrades and transmission service—Expected commercial operation, synchronization and withdrawal datesStudy-phase status and tariff-timeline deviations—2026-11-11
MISO——————2026-11-11
National Energy System Operator (NESO)CSV and CKAN Data API——Contracted effective connection dateProject build status and Gate 1/Gate 2 classificationTwice weekly: Tuesdays and Fridays2026-11-11
New York Independent System Operator (NYISO)—Large-load interconnection requests are reported in the Gold BookQueue position, owner/operator, project and zoneProposed in-service date; historical 2024 reporting, not a current wait estimate——2026-11-11
Pacific Gas and Electric (PG&E)XLSX download—————2026-11-11
PacifiCorp——County, state, region and point of interconnectionRequest date and customer-requested commercial operations dateRequest status and study schedule deviation—2026-11-11
PJM InterconnectionFull and filtered exports in XLS and XML—Filters by project type, cycle, status, transmission owner, state and county———2026-11-11
Southern California Edison (SCE)—WDAT and Rule 21 non-export requests accepted in tool————2026-11-11
Southern Company Transmission——Facility location, proposed POI, generation type/size and commentsQueue date and requested in-service date——2026-11-11
Southwest Power Pool (SPP)Public listing and CSV download—Capacity MW, summer/winter MW, generation/fuel type, POI and statusRequest received, withdrawal and commercial operation dates; cause of delayIncludes executed GIA and study stages—2026-11-11
Xcel Energy—————Monthly queue update2026-11-11

How much each ISO and RTO has queued

Full tracker

Storage includes estimated hybrid MW in LBNL’s regional summaries. Nuclear uses reported project-level MW. Total includes other resources. Waits cover completed projects with measured dates, not today’s applicants. Inspect each reading and its calculation.

What to compare between queues

How rows are read

Format and refresh

A queue you can download beats one you read. SPP and NESO offer CSV, PJM XLS and XML, PG&E XLSX. Refresh runs from twice a week at NESO to monthly at ERCOT, AESO and Xcel, and quarterly at Dominion, which also reports queue performance twice a year. The “Data as of” column shows the date printed on the page when we read it.

Dates are requests, not waits

Queues carry dates: request received, withdrawal, commercial operation. SPP lists all three and a cause of delay, PacifiCorp the customer-requested operation date, IESO the proposed in-service date. A proposed date is what the developer asked for. For measured waits use Berkeley Lab’s Queued Up, which measured a median 60.8 months from request to operation for the 294 projects built in 2025.

Fees, windows and thresholds

Entry terms differ by operator. MISO closes its 2026 DPP cycle on 15 January 2027. PG&E ran its QC16 cluster window from 11 to 25 September 2026. Xcel charges $300 for a Pre-Application Report in Minnesota, and BPA treats requests above 20 MW as large generators. Read the operator’s tariff before you file; each record links the page it comes from.